REGENTS
ROAD BRIDGE PROJECT WASTES MILLIONS
The City of San Diego spent an estimated $3 million on
an Environmental Impact Report (EIR) that they could
not defend in the face of our legal challenge because
it failed to fully disclose the negative impacts of the
Regents Road bridge project. The City hired a consultant,
Project Design Consultants (PDC), to include in the EIR
an unbiased analysis of a number of alternatives for
traffic congestion relief in addition to the Regents
Road bridge project. But secretly city staff promised
PDC a large contract to design the bridge (the most expensive
of those alternatives) if that alternative happened to
be “selected.” It was no surprise, then,
that PDC failed to disclose the severe negative impacts
of the bridge in the EIR – and millions in city
funds were wasted on a legally inadequate EIR that has
now been put on the shelf.
Read our two investigative reports.
These reports were prepared based on information found in city documents,
including internal emails. Most documents were discovered through Public Records
Act requests. The documents cited in these two reports are included as attachments.
Problems with the City’s Contracting Procedures
and the
Use and Misuse of North U.C. FBA Funds
Prepared for Greg Levin, Deputy Comptroller, City of San Diego
- Executive Summary
- Cover Letter and Body of Report (15
pages)
- Attachments (documents cited, 1-15)
- Attachments (16-29)
Legal, Ethical and Conflict of Interest Issues:
University City North/South EIR and Subsequent Actions
Point to Larger Problems
- Body of report (35 pages)
- Attachments 1-13
- Attachment 13 (legal size)
- Attachments 14-28
- Attachments 29 - 37
- Attachments 38-44
- Attachments 45-55
- Attachments 56-71
|